Gants Mill & Garden

Wedding venue in Somerset.   
Mill & garden visits.

Wedding venue - Greg
About us



Garden blog



Green energy from the watermill.
Green stuff,
accessibility

Links to wedding and garden websites.
Links


Somerset map showing where we are in Bruton.
Find us,
contact us

Site map
Site map


Home

Weddings Wedding reception ideas Day visits Garden Mill Hydropower
The water flowing from the mill leat into the millpool.
Lowering the penstock pipe into the waterwheel pit. The stimulus was provided by the need to reduce CO2 emissions, and the pledge by the Government to produce 10% of electrical energy from renewable resources by 2010.

At Gants Mill the new turbine was made by Valley Hydro of Cornwall, and the electronic mains connection unit by GP Electronics from Devon.

Left: Lowering the S-shaped penstock pipe though the floor into the old waterwheel pit.

Below right:
  Lowering the turbine. Inside is the turbine rotor, showing the 30 blades that turn the generator.
The plant was installed by Hydro Generation Ltd (now Renewables First).  Installation of the new turbine started in September 2003, and the staff of Hydro Generation tackled with enthusiasm the variety of engineering problems encountered.

All the pieces of the pipe work, turbine and generator were lowered into the old wheel pit using specialised heavy lifting gear.

Assembly of the parts required particular attention to the stresses and weights involved, with around 2 tonnes to be supported by RSJs slotted into the walls of the wheel pit.

Gaskets between each section were carefully compressed for the prevention of leaks.

Lowering the turbine. Inside is the turbine rotor, showing the 30 blades that turn the generator.
Near right:  Bolting the pipes together.

Far right:  The turbine lowered into position.

Below left: Diagram of the layout of the two turbines in the old waterwheel pit, with the original one on the right and the new one on the left.

Bolting the pipes together.

The turbine lowered into position.
Diagram of the layout of the two turbines in the old waterwheel pit, with the original one on the right and the new one on the left.

The support tower for the generator, keeping it above high water level.

Mounting the generator on the support tower.
Above: The support tower for the generator, keeping it above high water level. Above:  Mounting the generator on the support tower.
Turbine and generator completed, connected by belts.  At the same time electrical connections were being made, both to the external electricity pole on the grid, and within the mill itself.  Finally the time came for the testing and adjustment of all the working parts under operating conditions.  The installation was inspected by engineers from the electricity board to comply with G59 regulations for connection to the grid. Trenching for the electric cable between the generator and the local grid.
(Above)  Turbine and generator completed, connected by belts.  (Above)  Trenching for the electric cable between the generator and the local grid.
At the same time electrical connections were being made, both to the external electricity pole on the grid, and within the mill itself.  Finally the time came for the testing and adjustment of all the working parts under operating conditions.  The installation was inspected by engineers from the electricity board to comply with G59 regulations for connection to the grid. The turbine control panel Meter connection to the local grid.
Above: The turbine control panel. Above: Meter connection to the local grid.
The equipment is designed to produce up to 12 kW of electricity in continuous operation fed into the local grid. The unit shuts down completely in the event of any system failure or power cut.  The automatic operation also adjusts water flow through the turbine to maximise power output while maintaining a reserve flow of water in the main river. The actual output of electricity depends very much on river flow, being naturally greater during winter than in the summer months.

Adam Hart Davis launching the new hydropower scheme on Friday 23 April 2004, The turbine and generator's working life started on Friday 23 April 2004, when Adam Hart Davis visited to launch the scheme.  Visitors are able to see it as part of their tour of the mill during opening hours.

Over the centuries the mill has been adapted to society's changing requirements, as a corn mill, fulling mill, silk mill, then corn mill again, and is now a fine example of a small-scale hydropower scheme, producing electricity from a renewable resource.

Weddings: Greg Beedle
07854-166624 

Mill & garden visits: Elaine Beedle
07969-955442

Gants Mill & Garden
Bruton Somerset BA10 0DB  England